Construction Update

July 2nd, 2005

Buildings 1, 2, & 3 are now available for purchase!

Completion Dates
Building 1 November 2005
Building 2 September 2005
Building 3 October 2005

Road Repairs

July 2nd, 2005

All road repairs are expected to be completed in late September of this year. As long as weather permits this is the planned time frame and we thank you for your patience.

Start Brainstorming!

May 31st, 2005

We know moving into a new home can be exciting and nerve racking all at the same time!

To help future and current homeowners we are planning to setup an advice board in our Sales Office.

Tell us about your favorite local hangouts, decorating tips, moving tips and more! We also want to hear about your positive experiences living here at Auburn Park!

Please type or print legibly your tip and drop it off at the Sales Office. You may also e-mail, fax or call us with your tips! Let us know if you want to remain anonymous or we will state your first name only on the board along with your advice. This will give you a chance to stop in and check the board periodically to receive advice.

We hope that you will all take a moment to participate, as we believe this is another great opportunity to get to know your neighbors!

We look forward to hearing from you!

Thanks,
Kerry, Corinne and Anne

Construction Update

May 10th, 2005

Buildings 1, 2, & 3 will be released in early May.

Completion Dates
Building 15 June 2005
Bldg 16 July/Auguest 2005
Bldg 1 November 2005
Bldg 2 September 2005
Bldg 3 October 2005

Building 18 Driveways Poured

May 10th, 2005

The driveways for building 18 have been poured! They’re okay to walk on but please wait 8-10 days before driving on them.

Building 18 Driveway Framed

May 7th, 2005

The construction crew has finally framed building 18’s driveways.

Welcome!

April 28th, 2005

Welcome to the Auburn Park Condominium Community Website.

Residents are encouraged to Register. Registered users may post content to the site.